Monday, July 30, 2012

human rights


New Delhi : Seven states in north India woke up to a powerless Monday with supply cut at 2.32 a.m. due to a major breakdown in the grid that was not fully corrected till well into the afternoon, disrupting not just rail, metro and road traffic but also hospitals.
The preliminary reason for the power failure – one of the worst in a decade – was attributed to an outage in the northern grid, which is an interconnected transmission network that delivers electricity from various power generating stations to distribution utilities.
Apart from the national capital Delhi, supplies were sharply affected in Punjab, Haryana, Himachal Pradesh, Uttar Pradesh, Rajasthan and Jammu and Kashmir, said V.V. Sharma, general manager of Power System Operation Corp Ltd.
The company, a subsidiary of the state-run Power Grid Corp of India, which manages the grid, sought to restore power by supplies from the eastern and the western regions, even as power to the railways and Delhi Metro was restored by 9 a.m.
According to the company, parts of Badarpur in south Delhi, Narora and Simbhauli in Uttar Pradesh and Bhinma in Rajasthan were not hit by the tripping.
By afternoon, a semblance of normalcy was restored with most areas in north India getting electricity supply.
Power Minister Sushilkumar Shinde told reporters in New Delhi earlier that efforts were on to restore power supply on “a war footing”.
The minister denied that essential services were hit.
A three-member panel has been set up to look at the cause for the power failure.
With water treatment plants hit by the power failure, it was a double whammy for millions who had to contend with no power and no water as well.
The impact was felt in the critical healthcare sector.
All government hospitals, in the national capital, for instance, were put on emergency services and generator back-up.
According to railway officials, about 1.5 lakh passengers in around 300 trains suffered delays as the grid failure cripple operations across eights divisions of the Northern Railway.
Besides, about 200 goods trains had to be cancelled, resulting in an estimated loss of over Rs.100 crore, because passenger trains were given priority.
Many important trains like the Lucknow-Delhi Mail and overnight trains plying between New Delhi, Lucknow, Allahabad and Varanasi and Moradabad were stranded en-route, while some were brought to the nearest stations by diesel engines, a railway official said.
Delhi Metro services were restored fully only after two hours — at around 8.45 a.m.
A Delhi Metro official said they got hydel power from Bhutan on priority basis, and added that Delhi Metro was among the emergency services, including the prime minister’s residence and the All India Institute of Medical Sciences (AIIMS), that were provided power.
Power failure crippled most traffic signals in Delhi, causing massive traffic jams during office hours.
Delhi’s Indira Gandhi International Airport functioned normally with the help of generators.
In Uttar Pradesh, the power situation was almost normal in Lucknow and the eastern parts of the state by afternoon.
Hydro-power generation in Himachal Pradesh resumed Monday morning more than seven hours after the Northern Grid collapsed and stopped electricity production.
The state-run Himachal Pradesh State Electricity Board has 21 hydropower projects across the state with a combined optimum generation capacity of 8.5 million energy units a day   

http://www.learn-to-hack.com/

No comments:

Post a Comment